What does the "Dependency" feature in Smartsheet help manage?

Enhance your Smartsheet skills and prepare for certification with comprehensive quizzes and detailed explanations. Elevate your proficiency and confidence for the Smartsheet Certification Exam.

The "Dependency" feature in Smartsheet is designed to manage the relationships and schedules between tasks within a project. When you create dependencies, you establish links between tasks that dictate the order in which they should be completed. For instance, if Task B cannot start until Task A is finished, setting a dependency creates a clear timeline that helps ensure the project flows smoothly. This capability is essential for effective project management, as it allows teams to visualize task progression, prioritize work, and adjust schedules dynamically based on task completion.

While the other options address various aspects of project management, such as file attachments, team assignments, and budget tracking, they do not relate to the core function of managing task relationships and scheduling, which is central to dependencies in project planning.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy