Which view must include two date columns in order to be displayed?

  1. Card

  2. Calendar

  3. Gantt

  4. Grid

The correct answer is: Gantt

The Gantt view requires two date columns to be displayed because it relies on a start date and an end date to represent tasks on a timeline. This view visually depicts the duration of tasks, allowing users to see when tasks begin, how long they last, and how they overlap with other tasks. The two date columns provide the necessary information for creating the horizontal bars that represent each task along the Gantt chart, making it an effective tool for project management and scheduling. In contrast, the Card view primarily focuses on displaying tasks as cards typically organized by status or categories, which do not necessitate having two date columns. The Calendar view can show dates on a monthly, weekly, or daily basis but generally requires just a single date column for events. The Grid view is more focused on displaying data in a tabular format and does not depend on date columns to be functional, making the need for two date columns exclusive to the Gantt view.